ICDS |
III - CONSTRUCTION CONTRACTS |
||||||||||||||||||||||||
Scope:
This ICDS is applied to determine the income of a construction
contractor
Construction contracts - construction of single asset
-
construction of a no.of assets closely interrelated in terms
of
design,technology and function or ultimate use
Fixed
price contract
Construction contacts Cost plus contract
Segmenting
Each asset of a contract treated as separate construction contract
when:
·
separate proposals
submitted for each asset
·
each asset is capable of separate negotiation (contractor and customer have
option to accept or reject that part)
AND
·
cost and revenue of each asset is identifiable
Combining
Group of assets(with single customer or with several customers) will
be treated as single construction contract when:
·
group of contracts negotiated as single package
·
contracts very closely
interrelated (forming a single project with overall profit margin) AND
·
contracts performed concurrently or in
continuous sequence.
Construction of additional asset (at the customer's option or amendment to contract)
The construction of additional
asset treated as separate construction contract when:
·
asset differs
significantly from asset of original contract(in terms of
design,technology or function) OR
·
price of new asset negotiated without regarding the original contact price
Contract revenue
Recognition - When there is reasonable certainty of its ultimate collection
Comprises of - initial agreed amount of contract (incl
retentions) AND
- variations in contract work ,claims and
incentive payments:
·
to the extent its probable
that it will result in revenue AND
·
they are capable of being reliably measured
uncollectible contract
revenue - contract revenue
recognised as income
subsequently becomes uncollectible ,hence written off
recognisable as expense (NOT an adjst of contract revenue)
Contract Costs
Includes : cost for the period from the date of securing the
contract to final completion of
the
contract
cost of securing contract also included if:
·
they are seperatly identifiable
·
its probable that the contract shall be
obtained
If cost incurred for securing contract recognised as expense - not
included in contract cost if contract
obtained in subsequent period
Comprises of :
·
directly related
to specific contract
·
attributable
and allocable in general
·
specifically
chargeable to customer under the terms of contract AND
·
allocated borrowing
cost as per ICDS IX
Cost shall be reduced by incidental income(not being interest
,dividends or capital gains ),not included in contract revenue
Costs not attributable or
allocable to a contract -excluded from cost
Contract cost of future activity
Recognised as asset (amount
due from customer)
Classified as contract work in
progress
Recognition of contract revenue and expenses
·
percentage
completion method-recognised with respect to the stage of completion
of the contract activity at the reporting date
contract revenue matched with contract costs
incurred in reaching the stage of completion
resulting
in
reporting of revenue , cost and profit attributable to
the work completed
Determination of stage of completion of contract
Determined with reference to:
·
proportion of contract cost incurred for work
performed to the estimated total contract cost, OR
·
Surveys of work performed ,OR
·
Completion of a physical proportion of the
contract work
Progress
payments and advances received from customers not determinative of stage of
completion of contract
While determining stage of completion
by reference to the contract costs incurred upto the reporting date,only those costs that reflect work
performed are included in cost incurred upto reporting date.
Contract cost excluded-
·
costs related to future
activity
·
payments made to sub contractors in advance of work performed
Early stage if contract outcome of contract cannot be
estimated reliably
Contract revenue recognised
only to the extent of costs incurred
Early stage of contract shall
not extend beyond 25%of stage of completion
Changes in estimates
Percentage completion method
applied current estimates of contract revenue and
Costs
Change in estimates
Changed
estimates used for determination of
amount of revenue and expenses
In the
period in which change is made and for
subsequent periods
Transitional Provisions
·
Construction contracts commenced on or after 1.04.2016-.
contract revenue and cost recognisable as
per
the provisions of this standard
·
Construction contracts commenced on or before 31.03.2016 but not completed till date -
Contract
revenue and cost recognisable based on the method
regularly followed by the person prior to the
previous years beginning on the 1st day of April 2016
Disclosure
A person shall disclose:
·
amount of contract revenue
recognised as revenue in the period
AND
·
methods used to
determine the stage of completion of contracts
in progress.
Disclosures regarding
contracts in progress at the reporting date:
·
Amount of costs incurred and recognised
profits (less recognised losses) upto the reporting
date
·
the amount of advances received, AND
·
the amount of retentions
|
|||||||||||||||||||||||||
AS
|
VII- CONSTRUCTION CONTRACTS
|
||||||||||||||||||||||||
Point of differences :-
|
Contributed by Kashika Ahuja & Saino Susan at Sandeep
Ahuja & Co